You are trenching for a water main on dry land. At least how far ahead must you notify Sunshine 811 before you start digging?
On dry land you need at least 2 full business days. Underwater digs need 10 full business days.
Not less than 2 full business days before beginning any excavation or demolition that is not beneath the waters of the state, and not less than 10 full business days before beginning any excavation or demolition that is beneath the waters of the state…
Section 556.105(1)(a), Florida Statutes. Tab page 49 of the Sunshine 811 Damage Prevention Guide (2021) and highlight this line.